REA, filling the lighting gap to boost rural livelihoods, healthcare, and small businesses

0

“Granny Jennifer, a differently abled elderly and a widow of Lubanda Village in Chief Chikaza Munyama’s area in Itezhi-Tezhi, never imagined that her grass-thatched home would one day have electricity, as the standard K4,846 connection fee was far beyond her reach. –
Wednesday, July 2nd, 2025, Zambia Business Daily”

FB_IMG_1768725139388

Granny Jennifer, a differently abled elderly and a widow of Lubanda Village in Chief Chikaza Munyama’s area in Itezhi-Tezhi, never imagined that her grass-thatched home would one day have electricity, as the standard K4,846 connection fee was far beyond her reach. - Wednesday, July 2nd, 2025, Zambia Business Daily.

By Kelly Njombo

The arrival of affordable and reliable electricity marked the beginning of a new chapter not just for her, but her entire community in Itezhi-Tezhi District.

For years, small businesses and households in Granny Jennipher’s village and surrounding areas faced a daily struggle against lack of access to power, unreliable electricity, as well as soaring operating and connection costs.

Granny Jennifer, a differently abled elderly and a widow of Lubanda Village in Chief Chikaza Munyama’s area in Itezhi-Tezhi, never imagined that her grass-thatched home would one day have electricity, as the standard K4,846 connection fee was far beyond her reach. – Wednesday, July 2nd, 2025, Zambia Business Daily.

Granny Jennifer, a differently abled elderly and widow of Lubanda Village in Chief Chikaza Munyama’s area, never imagined that her grass-thatched home would one day have electricity, as the standard K4,846 connection fee was far beyond her reach.

However, thanks to the K300 subsidy connection project, she is now enjoying the comfort and dignity of a powered home, a powerful reminder that equitable access to energy changes lives.

“People like me don’t usually benefit from things like this. I still can’t believe I will sleep with lights tonight,” she said.

In an effort to increase rural electrification, the K300 electricity connection subsidy under the National Energy Advancement and Transformation (NEAT) project was last year launched and is being implemented by the Rural Electrification Authority (REA) and ZESCO Limited.

The subsidy which is made possible through a US$10 million facility supported by the World Bank, aims to deliver 23,695 new standard electricity connections to households and small and medium enterprises (SMEs) across rural Zambia.

The unique project continues to deliver tangible results in expanding access to electricity for under-served communities, with out of the 23,695 applications received during the subsidy window, a total of 17,114 households and small businesses have already been connected to the grid as of November 10, 2025.

The strong uptake reaffirms the critical role of the NEAT programme in making electricity affordable for rural and peri-urban communities.

In line with its mandate to expand electricity access in rural areas, REA from January 2025 to October 2025 made significant progress by broadening inclusive development and energy equity in various rural parts of the country, ensuring that even remote communities thrive through access to modern energy services.

REA Acting Manager Corporate Affairs Bright Chifulo disclosed that during the period under review, the Authority completed 45 projects and facilitated over 5,000 new household and institutional connections, significantly improving access to electricity in under-served communities.

Mr. Chifulo broke down the figures as follows, in the first quarter 13 projects were completed, delivering 856 new connections, second quarter saw 17 projects implemented, adding 1,631 connections, and in the third quarter 15 projects were finalised, resulting in 2,532 new connections.

Chifulo disclosed that during the period under review; REA successfully completed three major projects that have significantly expanded electricity access in rural Zambia.

These include the landmark K51 million Mitete Grid Development Project in Western Province, which now supplies power to an estimated 42,000 residents through 55 kilometres of concrete-pole grid infrastructure and a 550-metre Zambezi River crossing connecting the district to the national grid for the first time.

In Luapula Province, REA has also completed the K32.7 million Chishi Island Submarine Cable Project, delivering electricity to over 14,300 residents through a 32-kilometre under-lake and overhead cable system.

Similarly, the K11.53 million Lunga Electrification Project is fully complete, with 300 initial household connections already in place, benefiting an estimated 1,800 people as well as key facilities such as Lunga Primary Schools A and B, Itala Primary School and the New Apostolic Church.

Evidently, the completion of these projects has already begun to transform rural communities by improving livelihoods, strengthening public services and stimulating economic activity.

With reliable electricity available, health facilities in project areas now provide safer maternal care, operate life-saving equipment and maintain vaccine cold chains directly reducing maternal and infant deaths.

It is also worth noting that schools that previously relied on daylight can now support evening study, Information and Communication Technology learning and improved teacher retention, contributing to better education outcomes.

“Access to power has also boosted small businesses, enabling welders, barbershops, fish processing centres, Internet cafés, shops and agro-processing enterprises to operate more efficiently and for longer hours. Households that once depended on costly and unsafe energy alternatives now enjoy better lighting, enhanced security and lower living costs.

“Collectively, these benefits are helping reduce poverty by opening new income opportunities, enabling value addition and improving service delivery, thereby accelerating social and economic transformation in rural Zambia,” Mr Chifulo said in response to a query.

However, despite the Authority making commendable strides in expanding access to electricity across Zambia’s rural communities, several challenges continue to affect the pace and effectiveness of implementation.

Chifulo cited lack of affordability and low uptake of electricity connectivity due to various challenges.

“Despite the extension of electricity infrastructure to many areas, household connection rates remain low due to affordability constraints. Many rural families cannot afford the full connection fee, limiting the impact of these investments. To address this, REA is actively collaborating with Government and cooperating partners to reinstate and scale up connection subsidies. And this is where projects such as the NEAT comes in, which has already connected 17,114 households, demonstrating the trans-formative potential of targeted financial support,” Chifulo explained.

Other challenges include contractor performance and project delays; another significant challenge has been delays or stoppages caused by under-performing contractors who fail to meet project timelines or quality standards.

In response to the challenges, the Authority has taken decisive action by terminating contracts where necessary and engaging more capable contractors to ensure communities receive the reliable service they deserve.

However, to accelerate progress and improve delivery, REA is implementing a new subsidy programme, strengthening contractor performance monitoring, and enhancing procurement due diligence.

These measures aim to ensure timely, high-quality execution of electrification projects and bring sustainable energy access to more rural households across Zambia.

It is evident that access to reliable, affordable and sustainable electricity is critical for powering economies, delivering essential and health services, as well as spurring job creation for the country’s growing population.

Reliable power allows community enterprises to grow, the youth to innovate and households to improve their incomes and quality of life by boosting rural businesses such as salons and barbershops, welding shops and grain mills among others.

The deliberate investment in rural electrification by Government through REA is aimed at improving lives, stimulating economic growth at grassroots as well as ensuring improved health care services, as mothers deliver in safe and modern ways.

REA Acting Chief Executive Officer Engineer Alex Mbumba

In his new year message to the public, REA Acting Chief Executive Officer Engineer Alex Mbumba reaffirmed the Authority’s commitment to expanding access to electricity through grid extension and off-grid solutions in line with Government policy.

Government through the Energy Regulation Board (ERB) develops grid solutions especially for decentralised energy, through frameworks for mini-grids and smart grids, focusing on licensing, tariffs and technical standards to attract investment and ensure quality service for rural electrification.

Engineer Mbumba explained that in 2025 significant strides were achieved, and that the authority has set new targets for the year 2026, with more focus on electricity access and connectivity.

REA and ZESCO Limited have reaffirmed the two institution’s resolve to strengthen collaboration in order to accelerate the delivery of electricity connections and support Government’s target of achieving 100,000 new connections in 2026.

“We are grateful for the support you gave us in 2025. In 2026, we look forward to quite a number of things, building on what we achieved last year. In 2025, we implemented 62 projects out of the targeted 84 projects.

“So, this year we want to look at a very ambitious project which is focusing on more, mainly on access and connection. So, our target of 109,600 is what we intend to work with, and ensure that we achieve the target. The plan is to make such achievements in a similar manner this year,” Eng. Mbumba said.

To deliver affordable power and expand electricity access in Zambia, REA is implementing a number of projects in various parts of the country’s rural areas.

REA, which also recently unveiled its 2026 rural electrification plan, outlined a comprehensive programme to accelerate access to electricity across all ten provinces.

 

Minister of Energy Makozo Chikote

Led by REA board chairperson Charles Matomola Mboma and Eng Mumba, the Rural Electrification Authority presented its 2026 rural electrification plan to the Minister of Energy Makozo Chikote, a United Party for National Development (UPND) Luampa Constituency Member of Parliament (MP) Western Province.

The plan proposes the implementation of 149 projects, comprising 125 Grid Development Projects and 24 Off-Grid Projects, reflecting Government’s strategy of expanding the national grid while deploying sustainable energy solutions in remote and underserved areas.

The projects are expected to deliver 52,730 new electricity connections, benefiting 655 schools, 89 rural health centres, 80 public facilities, 53 traditional palaces, and 51,853 households nationwide.

REA emphasised that the plan is aligned with Government’s aspirations for inclusive development, balanced regional growth, and universal access to electricity, with a strong focus on improving service delivery, stimulating rural economies, and supporting climate-resilient and sustainable national development.

Mr. Chikote implored the REA team to work hard as rural areas still lagged in electrification of domestic, private and public buildings.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may have missed

绝妙集团公布50亿美元投资计划​作者:海伦·博瓦利亚(Hellen Bwalya)​绝妙集团有限公司(Wonderful Group of Companies Limited)通过其子公司赞比亚联合资本化肥有限公司(United Capital Fertilizer Zambia Company Limited),在其工业园区举行的奠基仪式上,正式启动了一项跨越2025年至2030年的50亿美元中长期工业投资宏伟计划。集团首席执行官黄耀弛先生在致答谢词时强调,该举措巩固了集团致力于提升赞比亚经济潜力、农业发展和就业水平的长期承诺。本次活动展示了多项价值数亿美元的制造业扩建及基础设施升级项目,旨在将赞比亚打造成中东非地区的核心工业强国。​在这项50亿美元的投资承诺中,园区内大规模的化工与化肥厂建设处于核心地位。继投资6.8亿美元的一期尿素生产厂竣工并投入运营后,集团正在稳步推进投资3.00亿美元的农化磷肥厂建设,预计将于第一季度投产,用于生产专用二铵(DAP)化肥。进一步的扩建计划还包括投资16亿美元的二期尿素项目和投资7.00亿美元的磷肥扩建项目,同时集团还将努力吸引更多绿色与高新技术投资者入驻运营。​为了支持这一工业增长并优化大宗运输物流,绝妙集团宣布了多项基础设施升级计划,包括升级连接当地矿山并穿过该工业园区的区域铁路网络、将蒙格维路(Mungwi Road)的部分路段改造为双向四车道,以及拓宽通往蒙布瓦路(Mumbwa Road)的连接线。这些基础设施项目将在完成内部财务手续后,通过政府与社会资本合作(PPP)模式实施,以畅通交通流量并缩短物资交付时间。黄耀弛先生对关键金融合作伙伴表达了谢意,向由艾莎银行(Absa Bank PLC)和赞比亚国家商业银行(ZANACO Bank PLC)牵头的银行银团为相关建设提供资金支持致以深切感谢。​在澄清公司身份时,黄耀弛先生指出,尽管早期外界存在误解,但绝妙集团和联合资本化肥公司均是值得骄傲的赞比亚本土企业。他强调,管理层中仅有两名中国籍员工,且均未直接参与日常运营,企业的行政控制权与管理权完全掌握在赞比亚本地人手中。黄耀弛先生重申了集团的承诺,并对赞比亚实现自产自销、对外出口以及引领东非和南部非洲工业未来的能力表达了坚定信心。